Plans, Procedures and Standards
- GreenerU Investment Grade Audits – 2021-Present
- Long Range Plan: Decentralizing Compressed Air on Campus – 2021-Present
- Strategic Energy 5-year Plan – 2016, 2019, 2021
- HMS Facilities Construction Design Standards includes Energy and Commissioning – 2016, 2022
- BAS Master Plan – 2015, 2021
-
Energy Audits
- GreenerU Main Dental & REB Audits– 2023-2024
- ASHRAE Level II Energy Audits – Completed for all buildings (2015-2019)
- Campus Compressed Air Systems – 2021-Present
- Campus Insulation – 2021-Present
- Campus-wide lighting audit – 2015-2022
- Greener U Investment Grade Audits #2, #3, #4 – 2022-2023
- Greener U Investment Grade Audits #5 – 2023-2024
- Kitchen Appliances & Water Audit – 2023
-
Water Conservation
- NRB Getinge Water Saver Kits for 22 Autoclaves – 2022
- NRB Quench Valve Replacements – 2020
- Low flow faucet aerators and shower heads – 2017
- Campus wide Water Audit performed – 2016
- Irrigation System Controls upgrade – 2015, 2021
-
Energy Dashboards and Information Systems
- Clockworks Analytics Fault Detection Software
- Internal Energy Dashboard – Retina
- Public Energy Dashboard from Altolus
- Data Historian and Visualization Platform OSI PiVision
-
BAS Improvement Initiatives
- BAS Desigo Upgrades – 2022-Present
- NRB BAS Transition to BACnet – 2022
- BMS Master spreadsheet – 2016
- Steam trap discharge sensors 2015 – 2016
- Transition from pneumatic actuation to DDC – 2016-2022
-
ACH Reduction
- HCCM Holding Rooms Spaces
- NRB/REB Rebalance of non-lab spaces to current ASHRAE/ IECC ventilation standards
- TMEC exhaust fan rebalance and consolidation
-
Occupancy Sensors for HVAC Setback and Lighting Control
- Mudd, LHRRB, C, 180 HSDM, REB, WAB
-
LED Lighting Upgrade Projects
- GreenerU South Campus & NRB Campus Lighting Upgrades – 2022-Present
- GreenerU Main Dental & REB Lighting Upgrades – 2024
- Replaced exterior HID Floodlight and wall pack fixtures to LED fixtures
- WAB Garage LED lighting upgrade
- Vanderbilt Hall LED exterior lighting project
- HCCM 4’ LED tube upgrade – NRB
- WAB HCCM LED lighting upgrade
- CFL to LED Lunera 4 pin lighting upgrade – 2,000+ Lamps
-
RCx and HVAC Energy Projects
- GreenerU NRB & WAB Heat Recovery Improvements – 2023-2024
- GreenerU NRB Heat Recovery Chiller Project – 2023-2024
- Mudd AHU-1 Chilled Water Valve Replacement – 2024
- TMEC AC-2 Chilled Water Valve Replacement – 2024
- TMEC AC-1 – 2021 to 2022
- NRB CoolTrol Installations Round 2 – 2021
- NRB Air Handling Units 5 & 6 Chilled Water Valve Replacements – 2021
- NRB Air Handling Units 7 & 12 Chilled Water Valve Replacements – 2022
- NRB Heating Ventilation Units 1, 2, 3 & 5 Steam Valve Replacements – 2021
- WAB Sterilizer Software Upgrade – 2022
- NRB HCCM – 2017
- Mudd HCCM – 2017
- WAB HCCM – 2016
-
Other
- Steam Trap Insulation Jackets (campus wide) – 2024
- Steam Trap Replacements (campus wide) – 2023-present
- Campus air handling units’ temperature sensor additions – 2023-present
- Campus wide steam insulation repairs & improvements – 2023-present
- NRB Solar PV System - 2021
- Ultra-Low Temp Freezer PM Program (240 Units) – 2015-2022
- Campus wide HVAC coil cleaning – 2016, 2021, 2023
- Campus doors weatherization – 2023